Explainers
Monte Carlo bid estimating: what P50, P80 and P90 mean
Monte Carlo simulation for bid estimators: model cost ranges, read P50, P80 and P90 and the chance of meeting a price, with a worked example and common mistakes.
A Monte Carlo simulation runs a cost model many times. Each run draws every uncertain input at random from a range you set, then records the total. After thousands of runs you have a distribution of possible costs instead of one number. From that distribution you can read percentiles, such as P80, the cost that 80 percent of runs stay at or below, and the share of runs that come in under a bid price.
Why one number hides risk
A single-point estimate adds up the most likely value of every cost line. That total is often below the typical outcome. Costs usually carry more upside risk than downside, through overruns, rework and delays, so the middle of the total tends to sit above the sum of the most likely figures. The worked example below shows that gap with made-up numbers.
A single number also says nothing about how likely it is to be wrong. Two bids with the same total can carry very different risk if one of them has wide ranges on its main cost drivers.
Model uncertain costs as ranges
For each cost line, estimate three values:
- Low: a realistic best case, not a hope.
- Most likely: your best single estimate.
- High: a realistic bad case, not the worst imaginable.
Use these for effort in hours, rates, quantities, material prices, subcontractor quotes and durations. A triangular distribution is a simple shape built from those three values. The PERT method uses the same three points with a smoother shape that gives more weight to the most likely value. Pick one shape, state it and keep it consistent. The shape matters less than whether the ranges are honest.
How to read P50, P80 and P90
Each percentile answers one question: how often does the cost stay at or below this value?
- P50 is the median. Half of the runs come in at or below it.
- P80 is the value that 80 percent of runs stay under.
- P90 is the value that 90 percent of runs stay under.
Two more readings matter for bidding:
- Chance of meeting a price. Count the share of runs whose total is at or below the bid. That is a probability under the model's assumptions, not a promise.
- Price for a target margin. If margin is measured on price, a price that gives margin m on cost C is C divided by (1 minus m). Apply that to a chosen percentile, for example P80, to get a bid that covers a high level of cost and still meets the target margin.
Which percentile to bid is a business decision. A competitive bid with little penalty risk might accept P50. A fixed-price contract with penalties for delay may justify P80 or P90. The model informs that choice but does not make it.
Worked example with made-up numbers
The figures below are illustrative. They were made up for this article and do not come from a real project, vendor or study. A real estimate needs your own ranges and your own history.
The example has three cost lines, in thousands of currency units:
| Cost line | Low | Most likely | High |
|---|---|---|---|
| Design | 8 | 10 | 16 |
| Build | 20 | 24 | 35 |
| Test and handover | 5 | 6 | 10 |
Each line is drawn from a triangular distribution with those three values. The model runs 100,000 times, adds the three draws each time, and treats the lines as independent. Across the runs:
- The sum of the most likely values is 40.0.
- The mean of the simulated totals is 44.6.
- P50 is 44.4.
- P80 is 47.9.
- P90 is 49.8.
Reading the results against bid prices:
- A bid of 40, the sum of the most likely values, covers the simulated cost in about 10 percent of runs.
- A bid of 45 does so in about 56 percent of runs.
- A bid of 50 does so in about 91 percent of runs.
- A bid near 48, the P80 value, covers the cost in about 80 percent of runs.
The single figure of 40 looks like the estimate. Under these assumptions, the total exceeds it most of the time.
Common mistakes
- Ignoring correlation. Costs often move together. A longer schedule raises labor, site overhead and equipment hire at the same time. Sampling each line on its own understates the spread of the total when costs move together. Model the link, or run scenarios in which the drivers move together.
- Ranges that are too narrow. People anchor on their best guess and draw tight ranges. Test your ranges against past projects. If they would have missed most of your past actual costs, they are too narrow.
- Ranges that are too wide. Very wide ranges make every bid look risky and tell you little. Anchor the ends of each range on evidence.
- Contingency on top of contingency. Adding a fixed 10 percent to a P80 total counts the same risk twice. Decide whether the chosen percentile already covers it.
- Missing risks. The model includes only the lines you add. Scope gaps, approval delays and client-driven changes stay invisible until they show up as costs.
- Treating P80 as a guarantee. It is a probability under the model's inputs. If the inputs are wrong, so is the probability.
Tools for the job
A simple model can be built in a spreadsheet with its random-number functions, for example in Microsoft Excel, which is part of Microsoft 365, or in LibreOffice Calc. A spreadsheet makes the logic visible, but it needs care with recalculation and with correlated inputs.
Dedicated bid-estimating software is another option. BidVariance* is a browser tool for fixed-price bids. It turns effort ranges into cost distributions and reports P50, P80 and P90. It is made by the publisher of listme.name, so it is marked as a connected product on the disclosure page. Compare it with spreadsheet models and other tools on what it does, and check its current licenses on the vendor's site.
What to do next
- Use the checklist for reading software rankings before you choose an estimating tool, and treat any ranking's method as part of the evidence.
- Record each estimate's ranges next to the actual cost when the job closes. Those records are the only reliable way to check whether your ranges are too narrow.
- For background on the method, see the Monte Carlo method on Wikipedia and the PERT article.
Mentioned in this article
Keep reading
All articles- Guides · 6 min readBest apps for students, organized by study taskPick study apps by task: notes, flashcards, tutoring, mind maps, writing, deadlines and reading. Includes the free plan limits that matter for each one.
- Roundups · 5 min readBest free alternatives to Microsoft OfficeCompare LibreOffice, ONLYOFFICE, Google Docs, WPS Office and Zoho Workplace, and learn where Microsoft file format compatibility can fall short for your documents.
- Comparisons · 5 min readLibreOffice vs Microsoft 365: Which Office Suite Should You Use?Compare LibreOffice and Microsoft 365 on price, desktop apps, sign-in, file sharing, open source and Office file support, and pick the suite that fits your work.







